EN 10204 3.1 vs 3.2: Which Certificate Should Fitting Buyers Request?

Oct 28, 2026 Leave a message

Request the inspection document required by the approved project specification and purchase order. EN 10204 Type 3.1 and Type 3.2 are not different stainless steel grades, and choosing 3.2 does not automatically add every possible test. The important differences concern validation responsibility and the inspection arrangements needed to support the document.

For pipe fittings, settle that requirement before comparing offers. A late request for "3.2 instead of 3.1" can affect inspection access, testing, traceability and delivery. It should not be treated as a change to the certificate heading alone.

Understand what the document type establishes

EN 10204 defines inspection-document types for metallic products. It works alongside the applicable product specification and order requirements; the document designation does not replace a fitting's material grade, manufacturing class, dimensions or specified acceptance criteria.

Both 3.1 and 3.2 report results of specific inspection. For 3.1, validation is by a designated manufacturer-side inspection representative who is independent of production. For 3.2, that manufacturer-side validation is accompanied by validation from the purchaser's authorized inspection representative or an inspector designated under official regulations. The inspection-document summary in TPS Technitube's technical catalogue sets out these roles.

Do not describe 3.1 as having no inspection simply because the validator is not an outside inspection company. Equally, do not interpret 3.2 as a promise that every fitting has received every test. The product standard, order and agreed inspection plan still determine the actual testing and coverage.

Use the project requirement as the decision gate

Read the piping specification, material requisition, equipment requirements and inspection plan together. If they conflict, obtain clarification from the responsible technical authority before award. A buyer should not downgrade a named document requirement for convenience, or add a more demanding arrangement without establishing its purpose and scope.

Situation Buyer's next step Resolve before release
The approved order accepts 3.1. Request 3.1 with the specified product test records. Correct validation, results and connection to the supplied fittings.
The approved order requires 3.2. Agree the authorized validation and inspection arrangements. Inspection scope, attendance, records and final document route.
Stock with 3.1 is offered against a 3.2 requirement. Refer the proposed verification route for approval. Whether the actual evidence and proposed document are acceptable.

The table is a purchasing workflow, not a rule that a particular service always needs one document type. Any regulatory or project-specific obligation must be checked for the actual application. A general product listing cannot settle that decision.

Plan the 3.2 inspection arrangements early

Identify the additional inspection representative and confirm that the proposed appointment is acceptable under the order. Agree an inspection and test plan covering the relevant manufacturing stages, review points, witness or hold points, test locations and reporting. Do not leave "third-party inspection included" as an undefined commercial note.

State who gives inspection notice, who arranges access to the manufacturer and laboratory, and who pays the agreed attendance and testing costs. Include the document-review and release responsibilities. These practical arrangements help avoid manufacturing or shipment progressing past a required inspection point without authorization.

Ask bidders to distinguish the certificate type from additional tests. If the project requires corrosion testing, PMI or extra examinations, specify the applicable method, extent, acceptance criteria and reporting separately. A document number is not a complete test schedule.

Treat stock-material verification as a technical proposal

Do not assume that an existing 3.1 certificate becomes 3.2 merely by adding a stamp. ABS describes an "intent of" Type 3.2 verification route involving material identification, traceability review, examination and supplementary testing with independent involvement.

Such a route must be assessed against the actual purchase requirement. Ask what document will be issued, what it will state, which activities will be performed and which original manufacturing activities cannot be verified. Obtain the required purchaser or project approval before assuming that an "intent of" certificate satisfies an order calling for 3.2.

If records, identification or access are inadequate, resolve that gap before accepting the stock. Do not change the original certificate wording or use a supplier's informal assurance as a substitute for the agreed validation process.

Connect the records to the finished fitting

A raw-material certificate and a finished-fitting inspection package answer different questions. Review what each document covers and how forming, heat treatment, welding or other relevant manufacturing operations are documented under the ordered specification. A matching alloy name on the input material is not the entire fitting acceptance package.

Before release, check:

  • The purchase line, product specification, grade, size and manufacturing designation.
  • Heat, lot or item identifiers against the fitting markings and packing records.
  • The required test results, test conditions and applicable acceptance limits.
  • Validator identities, roles and the agreed inspection or survey records.
  • Any exceptions, missing evidence and documented disposition before shipment.

If a document's authenticity or connection to the goods is doubtful, hold release and seek confirmation through the issuer's independently established contact or verification channel. A scanned signature or familiar inspection logo is not, by itself, proof that the delivered fittings are covered.

Put the requirement in the enquiry

When enquiring about Jiede's butt weld pipe fittings, state the EN 10204 edition and document type alongside the complete fitting specification. Include the required inspection plan, proposed validator arrangements and document-release conditions. Ask the supplier to confirm availability, scope and deviations in its quotation rather than assuming a particular certificate package from the product listing.